-
December 21st 2006: Signing of the Contract for the Project Manager and Egineer Consultants’ Services between Belgrade Land Development Public Agency, Serbia and Louis Berger Group Inc., USA
-
-
February 5th 2007: Mobilisation of PME and establishment of offices on Ada Ciganlija
-
-
April 04th 2007: Submission of Project Implementation Plan and Tender Documents for the Roads Designers
-
-
April 20th 2007: Prequalification for Bridge Contractors launch
-
-
May 31st 2007: Development of complete Tender Documents for the Bridge Works Contract
-
-
June 04th 2007: Prequalification for Bridge Contractors returned
-
-
July 09th 2007: Launching of the tenders for the Detailed Designs of the South Approach Roads and Pastroviceva Street
-
-
July 19th 2007: Bridge Tender issued
-
-
July 30th 2007: Contract Award for the North Approach Roads Detailed Design
-
-
August 16th 2007: Submission of Environmental Action Plan rev. 1
-
-
September 14th 2007: Submission of Technical Supervision of the Bridge Works Tender Dossier
-
-
September 14th 2007: Contract Award for Paštroviceva Street Detailed Design
-
-
September 21st 2007: Contract Award for South Approach Roads Detailed Design
-
-
October 09th 2007: Submission of Prequalification and Draft Tender Documents for Supervision of Approach Roads
-
-
October 17th 2007: Bridge Tenders returned
-
-
December 07th 2007: Submission of Bridge Draft Tender Report
-
-
February 04th 2008: Client's Approval of Tender Documents for Approach Roads Works and Supervision
-
-
February 12th 2008: EBRD approval to Bridge Tender Report received
-
-
April 09th 2008: Signing of the Sava Bridge Design and Build Contract with PORR Technobau und Umwelt AG; SCT dd; DSD Bruckenbau GmbH Consortium
-
-
May 21th 2008: Commencement of Works - Sava Bridge.
-
-
October 15th 2008: Site installation works - Sava Bridge.
-
-
December 1st 2008: First trial pile on pier 7 - Sava Bridge.
-
-
March 06th 2009: Launching of the Tender for Hipodrom interchange on Cukarica side - SAR
-
-
April 16th 2009: First Work Contract Award for South Approach Road section, Hippodrome Interchange (Section 1A) to the Joint Venture Ratko Mitrovic – Novcol – Hidropromet Inzenjering.
-
-
April 20th 2009: Engineer's inspection of the Bridge fabrication shop in China
-
-
April 29th 2009: Sava Bridge site 2 hand over
-
-
May 07th 2009: First Approach Roads works contract agreement, for Hippodrome Interchange, signed with Joint Venture Ratko Mitrovic – Novcol – Hidropromet Inzenjering
-
-
May 08th 2009: Launch of the Bridge Technical Supervision Tender
-
-
May 31st 2009: President of Republic of Serbia and Mayor of Belgrade visit Sava Bridge Site
-
-
June 01st 2009: Start of Bridge steel segments fabrication in China.
-
-
July 10th 2009: Signing of the Bridge Technical Supervision Service Contract
-
-
July 13th 2009: Launch of tender for Radnicka Street Interchange Design Competition
-
-
July 17th 2009: Completion of piling works at Bridge Pylon location
-
-
August 25th 2009: Bridge Contractor concrete? first section of the Bridge superstructure
-
-
August 29th 2009: First delivery of fabricated steel structural elements to site (back span struts)
-
-
September 07th 2009: Issuance of the Building Permit for Hippodrome Interchange
-
-
September 16th to 18th 2009: Biggest single concrete pour in the Project – 2800 m3 for the first part of the Bridge Pylon pile cap
-
-
September 16th 2009: Belgrade Mayor's Visit to Site
-
-
September 28th and 29th 2009: Engineer's visit to Vorspann Technik facilities in Salzburg and Munich
-